Current Construction Projects:
TxDOT
IH 45, S. LP 336 to N. LP 336 – Only Clean-up remaining – Completion Summer 2012
IH 45, N. LP 336 to FM 830 – Completion Spring 2013
IH 45, FM 830 to Calvary Rd. – Completion Summer 2014
IH 45, Calvary Rd. to 1.1 miles S. of Walker Co. line – Completion Summer 2013
IH 45, 1.1 miles S. of Walker Co. line to Walker co. line – Only Clean-up remaining – Completion Summer 2012
Future Construction Projects:
TxDOT
SH 105 W. widening from Walden Rd. to Old River Rd. – Letting October 2012
SH 105 E. “Super 2” (Passing lanes) from E. LP 336 to Liberty Co. line – Letting Fall 2012
FM 3083 widening from IH 45 to E of SH 75 – Letting Summer 2013
TxDOT with Montgomery Co.
SH 242 Direct Connectors with IH 45 – Letting August 2012
Woodlands Parkway Expansion – Letting August 2012
CISD
New Peet Jr. High on Longmire Rd N of LP 336 will open Fall 2013
Airport
Runway Extension – Still waiting on 30% Funding
Three Story Building with Blackforest Restaurant at the end of Hawthorne Rd. – Completion 1 year